Case study Boiler replacement project at University of Lincoln

16 Feb 2023

Background

Lincoln Courts is a modern waterfront accommodation complex, situated in the heart of the Student Village. Owned and managed by the University of Lincoln, the complex is made up of 17 contemporary buildings of self-catered apartments, each housing five to eight students and some apartments are specifically designed for students with disabilities.

Brief

To provide detailed design, supply, installation, testing and commissioning of new gas fired, modular boiler systems, to serve student accommodation in Courts 15, 16 and 17.

Summary of works provided

Ancillary works to existing mechanical and electrical services in each plantroom were completed to facilitate boiler replacement. Mechanical works comprised boiler installation, main header distribution pipework, valves, pressurisation equipment and condensate discharge pipework. Electrical works included individual plant power supplies, BMS control interfaces, safety interlocks and control panel modifications. Our inhouse consultant engineer designed the systems to integrate with existing site-wide Delta Controls BMS. We assessed the existing low temperature hot water (LTHW) distribution system serving each Court to verify the required heating load of the new boiler plant.

The team needed to address several challenges, one being limited access to the plantrooms located on the top floor of each building and accessed via internal staircases.

Lift and shift equipment was used to safely remove and transport equipment to and from the plantrooms which involved the use of stair-climbing equipment, mechanical material hoists and shifting skates.

All new plant and equipment needed to fit within the existing space allocations of the plantrooms, whilst maintaining the required spacings for individual concentric flue terminations. Our inhouse consultant engineer chose a frame mounted, cascade boiler system to allow the plant footprint to fit within the allocated space and create space behind to route the boiler flue systems.

All work on Courts 15 and 16 had a ten week completion schedule, however, Court 17 had a tight four week schedule as returning students needed occupancy.

In response, our team developed a detailed programme of activity identifying key milestones and co-ordinating individual work packages of all contractors involved, successfully completing works on time and to budget.

The existing boiler plant was no longer manufacturer supported increasing the risk of operational inefficiencies, unreliability and potential downtime. The new boiler systems provide the University with peace of mind and the modular system ensures plant redundancy should one of the boilers develop an issue.

Seasonal efficiency of the boilers is 95.44%, compared to an estimated 70% of those replaced. This has resulted in reduced gas consumption and operational savings, and the new boiler systems have a life cycle of 15+ years.

Case Studies

The Picture House

Read More >

One St Peter's Square

Read More >

Kaye's Academy

Read More >

Elk Mill Retail Park

Read More >

Welcome Finance

Read More >

Lateral House

Read More >

Serpentine Galleries

Read More >

Extra MSA

Read More >

Withington Girls School

Read More >

Princesshay Shopping Centre

Read More >

Crowngate Shopping Centre

Read More >

IKEA - Livat Hammersmith

Read More >

Replacement boiler system & BEMS at Morses Club plc

Read More >

Chiller installation at Derwent House

Read More >

HVRF solution design & installation at BAT - Building 25

Read More >

Power outage at Princesshay Shopping Centre

Read More >

Kitchen fire damage at Cobham MSA

Read More >

Flood damage at Twenty Chapel Street

Read More >

Crowngate Shopping Centre

Read More >

The Guinness Partnership

Read More >